Question: What information is usually provided on a resource - usage calendar? Group of answer choices The personnel, their hourly wage or salary, and the number

What information is usually provided on a resource-usage calendar?
Group of answer choices
The personnel, their hourly wage or salary, and the number of hours per week they are available.
The personnel, their responsibility for certain tasks, and the number of hours per week they are available.
The tasks, the precedence requirements, and the money per unit time needed to reduce them.
The tasks, the people and equipment available, and the ownership and reporting relationships among them.