Question: what is hard power AaBbcode AaBbccde AaBb Cel Aal Emphasis Heading 2 1 Normal Strong Subtitle Title Paragraph Styles Q4.An Italian engineering project has the

what is hard power
what is hard power AaBbcode AaBbccde AaBb Cel Aal
AaBbcode AaBbccde AaBb Cel Aal Emphasis Heading 2 1 Normal Strong Subtitle Title Paragraph Styles Q4.An Italian engineering project has the following activities, whose time estimates are listed as follows Activity Optimistic 12 2 4 1-2 1-3 1-4 2-5 3-5 4-6 5-6 Estimated Duration in months) Most Likely Pessimistic 2 14 8 14 4 16 2 2 10 28 10 116 12 30 2 4 4. 6 (a)Find the critical path for the project (10 marks) Answer and show workings here)