Question: What is the additional cost of reducing the project completion time to 35 weeks? Task Description Estimated Activity Cost Available Crash Time Total Crash Cost

What is the additional cost of reducing the project completion time to 35 weeks?

Task Description Estimated Activity Cost Available Crash Time Total Crash Cost
A Requirements $ 10,000 0
B Market Assesment $ 20,000 2 $ 25,000
C Design $ 15,000 1 $ 30,000
D Development $ 45,000 2 $ 65,000
E Testing $ 10,000 2 $ 20,000
F Revisions $ 15,000 2 $ 18,000
G Documentation $ 20,000 4 $ 30,000
H Quality Assurance $ 10,000 2 $ 15,000
I Pricing $ 5,000 0
J Production $ 40,000 2 $ 50,000
K Distribution $ 15,000 0