Question: What is the approximate cost to complete the project under normal conditions? Question 46 options: $45,000 $50,000 $55,000 $65,000 $70,000 Question 47 (2 points) How
What is the approximate cost to complete the project under normal conditions?
Question 46 options:
|
| $45,000 |
|
| $50,000 |
|
| $55,000 |
|
| $65,000 |
|
| $70,000 |
Question 47 (2 points)
How long will it take to complete the project under normal conditions?
Question 47 options:
|
| Fewer than 17 days |
|
| 18 days |
|
| 20 days |
|
| 22 days |
|
| More than 23 days |
Question 48 (2 points)
Using the information in the table, the project manager decided to complete the project in 17 days. What is the cost of crashing to achieve this goal?
Question 48 options:
|
| $1,500 |
|
| $4,000 |
|
| $4,500 |
|
| $3,000 |
|
| $7,000 |
Question 49 (2 points)
When crashing the schedule, what is the shortest duration to complete the project?
Question 49 options:
|
| 13 |
|
| 14 |
|
| 15 |
|
| 16 |
|
| 17 |
Question 50 (2 points)
If there is a penalty of $5,000 per day, what is the optimal completion time for completing the project (i.e., the saving from not paying the penalty ($5,000/day) is greater than crashing cost per day)?
Question 50 options:
|
| 14 |
|
| 15 |
|
| 16 |
|
| 17 |
|
| 18 |