Question: What is the approximate cost to complete the project under normal conditions? Question 46 options: $45,000 $50,000 $55,000 $65,000 $70,000 How long will it take

What is the approximate cost to complete the project under normal conditions?
Question 46 options:
|
| $45,000 |
|
| $50,000 |
|
| $55,000 |
|
| $65,000 |
|
| $70,000 |
How long will it take to complete the project under normal conditions?
Question 47 options:
|
| Fewer than 17 days |
|
| 18 days |
|
| 20 days |
|
| 22 days |
|
| More than 23 days |
Using the information in the table, the project manager decided to complete the project in 17 days. What is the cost of crashing to achieve this goal?
Question 48 options:
|
| $3,000 |
|
| $1,500 |
|
| $4,500 |
|
| $7,000 |
|
| $4,000 |
When crashing the schedule, what is the shortest duration to complete the project?
Question 49 options:
|
| 13 |
|
| 14 |
|
| 15 |
|
| 16 |
|
| 17 |
If there is a penalty of $5,000 per day, what is the optimal completion time for completing the project (i.e., the saving from not paying the penalty ($5,000/day) is greater than crashing cost per day)?
Question 50 options:
|
| 14 |
|
| 15 |
|
| 16 |
|
| 17 |
|
| 18 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts