Question: What is the cost performance index for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC
-
What is the cost performance index for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.
1.25
0.8
1.1
0.91