Question: what is the CPI, EAC and scedule variance ? We are now part way through a project at a point where we had planned to
what is the CPI, EAC and scedule variance ?
We are now part way through a project at a point where we had planned to have 49% of the work done. We have spent $338,918 of the total budget of $717,944. We have completed 79% of the activities. What is the EV? (pick closest answer)
Step by Step Solution
There are 3 Steps involved in it