Question: What is the critical path for the same table? Normal Normal Activity Immediate Time Predecessors (weeks) A None 4. B A 9 A 4 D

What is the critical path for the same table?
What is the critical path for the same table? Normal Normal Activity Immediate Time Predecessors (weeks) A None 4. B A 9 A 4 D B,C 6 E C 8 F D 3 G E, F 4 O A, B, D, F, G O A, C, E, F,G