Question: What is the critical path for this project and how long is it? 1. Consider Table Q1. All duration estimates or estimated times are in

What is the critical path for this project and

What is the critical path for this project and how long is it?

1. Consider Table Q1. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. TABLE Q1 Network diagram data for a small project Activity Inillal Node Final Node Estimated Duration A 1 2 2 B 2 2 2 + 3 D 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 1 6 7 5 J 7 8 1 K S 9 2 O Cenga Leaming 2014