Question: Consider the following table, showing the activities and duration estimates of a project: Activity Initial Final Node Duration Node Estimate/ days A 1 2 2

Consider the following table, showing the

Consider the following table, showing the activities and duration estimates of a project: Activity Initial Final Node Duration Node Estimate/ days A 1 2 2 IB 1 13 13 C 11 14 14 D 2 3 14 E 3 5 3 IF 14 15 4 G 3 16 15 H 5 6 4 a) Draw an AOA diagram representing the project. (3) b) Identify all the paths on the AOA diagram and calculate how long they are. (3) c) What is the critical path for the project and how long is it? (1) d) What is the earliest possible time it will take to complete this project? (1) e) identify 2 nodes acting as bursts (1) f) identify 2 nodes acting as merges (1)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!