Question: What is the critical path in the chart above? Using the critical path method, what would be your proposal to reduce the total time by

What is the critical path in the chart above?

What is the critical path in the chart above? Using the critical path method, what would be your proposal to reduce the total time by 3 weeks? Explain your rationale.

B(4) $1K D16) $5K G(3) $15K A(4) $12K F(6) $5K J(3) $12K C(9) $15K E(5) $8K H(4) $5K Time in Weeks