Question: What is the critical path(s) and the completion time for the project? A. Path A-B-F, 19 days B. Path A-B-F, 20 days C. Path C-D-E-F,

- What is the critical path(s) and the completion time for the project?
A. Path A-B-F, 19 days
B. Path A-B-F, 20 days
C. Path C-D-E-F, 19 days
D. Path C-D-E-F, 20 days
E. Paths A-B-F and C-D-E-F, 20 days
- If you crash this project to reduce the total time by one day as long as the crashing cost is less than $1,000, which activity (activities) should you crash?
A. Activity A
B. Activity B
C. Activity C
D. Activity D
E. Activity E
- If you crash this project to reduce the total time by a second day as long as the crashing cost is less than $1,000, which activity (activities) should you crash?
A. None
B. Activity B
C. Activity E
D. Activities B and C
E. Activities B and E
Use the diagram to answer the following three questions. A(7) B(10) Start F(2) C(5) D(4) E(9) For the network shown above, the project indirect cost for each day is $1,000. The following is the crashing information: Number of days activity may Activity Cost per day to crash be shortened/crashed $250 $300 $600 2 B 1 EStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
