Question: What is the difference between Program evaluation and review technique and Critical path method? They differ in terminology and in the construction of the network.

What is the difference between "Program evaluation and review technique" and
"Critical path method"?
They differ in terminology and in the construction of the network.
PERT ignores activity costs.
PERT assumes that activity durations are known.
CPM assumes that activity durations can vary.
PERT is more accurate than CPM.