Question: What is the earliest start time for activity D in the following diagram? start B3 E1 finish A4 C2 D7 F2 O a. 7 O

What is the earliest start time for activity D inWhat is the earliest start time for activity D inWhat is the earliest start time for activity D in

What is the earliest start time for activity D in the following diagram? start B3 E1 finish A4 C2 D7 F2 O a. 7 O b.4 O c. 6 O d. 3 In a PERT network the time required to complete a path is a(n) a. constant o b. exponentially distributed variable c. Poisson distributed variable d. random variable What are the immediate predecessors of activity D in this network? start B 3 E1 finish A4 C2 D7 F2 O a. E, F b. B, C OC. A, B, C d. E, G, H