Question: What is the earliest that Activity D can begin based on the data provided in the following table? Activity - Optimistic Time - Most Likely

What is the earliest that Activity D can begin based on the data provided in the following table?
Activity - Optimistic Time - Most Likely Time - Pessimistic Time - Predecessor
A -5-6-7-
B -2-3-10- A
C -4-5-6- A
D -7-10-13- B
Options:
Day 9
Day 10
Day 11
Day 12