Question: What is the earliest that activity E can start given the predecessor relationships and task times shown in the following table? Activity Predecessor Duration A

What is the earliest that activity E can start given the predecessor relationships and task times shown in the following table?

Activity

Predecessor

Duration

A

None

5

B

None

6

C

None

7

D

None

8

E

A, B, C, D

5

Group of answer choices

10

The early finish time of activity A

13

8

5