Question: What is the earliest this project can be completed? State your answer in number of daysnumber only. Task Days Immediate Predecessor A 4 None B

What is the earliest this project can be completed? State your answer in number of daysnumber only.

Task Days Immediate Predecessor

A 4 None

B 5 A

C 3 A,B

D 4 C

E 5 B

F 6 E,D