You are responsible for managing a project with the following activities. What is the minimum crashing cost to finish the project in 18 days?
Activity | Predecessor | Normal Time (days) | Maximum Crash Time (days) | Crashing Cost/day |
---|---|---|---|---|
A | -- | 5 | 1 | $200 |
B | -- | 7 | 1 | $500 |
C | -- | 5 | 1 | $200 |
D | A | 10 | 2 | $300 |
E | B | 6 | 1 | $400 |
F | A, C | 7 | 2 | $650 |
G | B | 4 | 1 | $500 |
H | E, D, G | 6 | 1 | $350 |
Select one:
a. $1,500
b. $1,150
c. $850
d. $3,450