Question: What is the early start time for Activity D given the activity times and precedence requirements shown in the table? table [ [ Activity

What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
\table[[Activity,Time,Predecessor],[A,5,-],[B,8,A],[C,4,A],[D,5,B, C]]
A)5
B)9
C)13
D)18
7. What is the slack time for Activity B given the activity times and precedence requirements shown in the table?
\table[[Activity,Time,Predecessor],[A,4,-],[B,7,-],[C,8,A],[D,2,A],[E,4,B],[F,5,C, D],[G,9,E, F],[H,7,G]]
A)7
B)6
C)5
D)4
8. Use the information in the table to determine the late start time for Activity E.
\table[[Task,Predecessor,Duration,\table[[Early],[Start]],\table[[Early],[Finish]],Late Start,\table[[Late],[Finish]]],[A,F,8,,,,],[B,A,,,,14,],[C,A,,,23,8,],[D,C,B,6,23,,26,],[E,C,,,32,,],[F,D,E,,32,,,38]]
A) day 23
B) day 26
C) day 32
D) day 17
 What is the early start time for Activity D given the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!