Question: What is the estimate for the work associated with summary task 1 . 1 Site Prep? table [ [ WBS , Task,Estimated Duration ]

What is the estimate for the work associated with summary task 1.1 Site Prep?
\table[[WBS,Task,Estimated Duration],[1.0,House Project,],[1.1,Site Prep,],[1.1.1,Excavate and pol footers,9 days],[1.1.2,Pour concrete footers,5 days],[1.1.3,Site Prep Complete,0 days],[1.2.0,Framing and Brickwork,],[1.2.1,Erect wooden frame including rough roof,10 days],[1.2.2,Lay brickwork,8 days],[1.2.3,Framing and Brickwork Complete,0 days]]