Question: What is the estimated expected ( mean ) time for activity E ? table [ [ Activity , table [ [ Immediate ]

What is the estimated expected (mean) time for activity E?
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Optimistic Time],[Estimates (days)]],\table[[Most Likely Time],[Estimates (days)]],\table[[Pessimistic Time],[Estimates (days)]]],[A,-,44,50,56],[B,-,45,60,75],[C,A,42,45,48],[D,A, B,31,40,49],[E,C,27,36,39],[F,D, E,58,70,82]]
36 days
40 days
45 days
35 days
39 days