Question: Consider the following work breakdown structure: Activity Start Node Finish Node Time Estimates ( wks ) to tm tp A 1 2 1 1 2
Consider the following work breakdown structure:
Activity Start Node Finish Node Time Estimates wks
to tm tp
A
B
C
D
E
What is the estimated expected mean time for activity E
Multiple Choice
weeks
weeks
weeks
weeks
weeksConsider the following work breakdown structure:
points
What is the estimated expected mean time for activity E
Multiple Choice
weeks
weeks
weeks
weeks
weeks