Question: What is the estimated expected ( mean ) time for project completion? table [ [ Activity , table [ [ Start ] ,

What is the estimated expected (mean) time for project completion?
\table[[Activity,\table[[Start],[Node]],\table[[Finish],[Node]],\table[[Optimistic Time],[Estimates (days)]],\table[[Most Likely Time],[Estimates (days)]],\table[[Pessimistic Time],[Estimates (days)]]],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,,32,41,44]]
221 days
41 days
100 days
120 days
70 days
 What is the estimated expected (mean) time for project completion? \table[[Activity,\table[[Start],[Node]],\table[[Finish],[Node]],\table[[Optimistic

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!