Question: What is the estimated expected (mean) time for activity D? Activity Start Node Finish Node Optimistic Time Estimates (days) Most Likely Time Estimates (days) Pessimistic

What is the estimated expected (mean) time for activity D?

Activity

Start

Node

Finish

Node

Optimistic Time

Estimates (days)

Most Likely Time Estimates (days)

Pessimistic Time

Estimates (days)

A

1

2

41

50

59

B

1

3

54

60

66

C

2

4

58

70

82

D

3

4

32

41

44

32 days

41 days

44 days

42 days

40 days