Question: Activity Immediate Predecessor Optimistic Time Estimates ( days ) Most Likely Time Estimates ( days ) Pessimistic Time Estimates ( days ) A _ 4

Activity
Immediate Predecessor
Optimistic Time
Estimates (days)
Most Likely Time
Estimates (days)
Pessimistic Time
Estimates (days)
A
_
44
50
56
B
_
45
60
75
C
A
42
45
48
D
A, B
31
40
49
E
C
27
36
39
F
D, E
58
70
82
40 weeks
39 weeks
31 weeks
38 weeks
43 weeks