Question: What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3 , 4 and 7 days respectively?
What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of and days respectively?
a
b
c
d
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
