Question: What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3 , 4 and 7 days respectively?

What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3,4 and 7 days respectively?
a.3
b.4
c.4.3
d.4.7