Question: What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 6,7, and 10 days respectively? 9.33 6.33

What is the expected time to complete a task with

What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 6,7, and 10 days respectively? 9.33 6.33 7.33 10.33 8.33

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock