Question: What is the first job to be started if we decide that our priority sequencing rule is Order Slack? Job Remaining Processing Remaining Work Shortest
What is the first job to be started if we decide that our priority sequencing rule is Order Slack?
| Job | Remaining Processing | Remaining Work | Shortest Step | Setup Time | Run Time | Number of Ops |
| 1 | 34 | 144 | 6.2 | 1.5 | 3.2 | 8 |
| 2 | 78 | 76 | 3.2 | 1.4 | 3.8 | 8 |
| 3 | 177 | 124 | 3.8 | 1.9 | 4.9 | 5 |
| 4 | 130 | 802 | 1.8 | 5.0 | 4.6 | 7 |
| 5 | 66 | 37 | 10.8 | 7.4 | 4.0 | 9 |
| 6 | 32 | 97 | 7.8 | 9.6 | 5.6 | 5 |