Question: What is the first thing that should happen when a new change request comes in ? A It should be analyzed for feasibility. It should

What is the first thing that should happen when a new change request comes in?
A It should be analyzed for feasibility.
It should be added to the change request log and assigned a tracking number.
C Examine whether the person or entity submitting the change request is a valid stakeholder in the project.
The project sponsor is notified.
 What is the first thing that should happen when a new