Question: What is the function of a work breakdown structure? Multiple choice question. Provides the basis for detailed time and cost estimates on a project Provides
What is the function of a work breakdown structure? Multiple choice question. Provides the basis for detailed time and cost estimates on a project Provides an example to other projects of how not to manage interpersonal dynamics Used to generate risks and opportunities for successful project management