Question: What is the function of the precedent diagramming method? A. To identify non work days such as holidays and weekends B. To show the dependencies
What is the function of the precedent diagramming method? A. To identify non work days such as holidays and weekends B. To show the dependencies between project activities C. To show the cost estimates of project activities D. All of the above