Question: What is the late finish ( LF ) time for activity H ? a . 1 7 b . 1 2 c . 1 4

What is the late finish (LF) time for activity H?
a.
17
b.
12
c.
14
d.
19
e.
9Use the information below to construct a project network using the activity-on-node (AON) methoc
in order to answer questions that follow.
 What is the late finish (LF) time for activity H? a.