Question: table [ [ Predecessor , Duration ( in days ) ] , [ None , 3 ] , [ A , 1 ] ,
tablePredecessorDuration in daysNoneAABB CEDEF G HI
What is the earliest start ES time for activity G
Identify the critical path
a
b
c
d
e
Which activity has a slack of days?
a Activity
b Activity E
c Activity
d Activity J
e None of the above
a ACEFIJ
b ABDGIJ
c ABEF
d ABEFIJ
e ACEHIJ
What is the late finish LF time for activity J
a
b
c
d
e
is the late finish LF time for activity
d
e
e
rmine the duration it will take to complete this project using the AON method
a days
b days
c days
d days
e days
It is the late finish LF time for activity F
a
b
c
d
e
at is the earliest start ES time for activity l
a
b
c
d
e
Activity is delayed by days. What will happen to the rest of the project?
a The whole project will be delayed by days
b There will be no impact on the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock