Question: table [ [ Predecessor , Duration ( in days ) ] , [ None , 3 ] , [ A , 1 ] ,

\table[[Predecessor,Duration (in days)],[None,3],[A,1],[A,4],[B,1],[B, C,2],[E,8],[D,2],[E,3],[F, G, H,1],[I,1]]
What is the earliest start (ES) time for activity G?
Identify the critical path
a.5
b.7
c.9
d.11
e.17
Which activity has a slack of 10 days?
a. Activity D
b. Activity E
c. Activity H
d. Activity J
e. None of the above
a. ACEFIJ
b. ABDGIJ
c. ABEF
d. ABEFIJ
e. ACEHIJ
What is the late finish (LF) time for activity J?
a.19
b.18
c.17
d.16
e.15
is the late finish (LF) time for activity H?
17
12
14
2.14
d.19
e.9
e.7
q,
rmine the duration it will take to complete this project using the AON method
a.19 days
b.20 days
c.14 days
d.9 days
e.11 days
It is the late finish (LF) time for activity F?
a.17
b.16
c.21
d.19
e 7
at is the earliest start (ES) time for activity l?
a.7
b.17
c.12
d.15
e.9
Activity F is delayed by 2 days. What will happen to the rest of the project?
a. The whole project will be delayed by 2 days
b. There will be no impact on the project
 \table[[Predecessor,Duration (in days)],[None,3],[A,1],[A,4],[B,1],[B, C,2],[E,8],[D,2],[E,3],[F, G, H,1],[I,1]] What is the earliest start

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!