Question: Activity Precedes Optimistic Most Likely Pessimistic Start A , B , C - - - A D 3 8 5 0 6 2 B E

Activity
Precedes
Optimistic
Most Likely
Pessimistic
Start
A,B,C
-
-
-
A
D
38
50
62
B
E
90
99
108
C
End
85
100
115
D
F
19
25
31
E
End
91
100
115
F
End
62
65
68
What is the estimated expected (mean) time for activity E?
A.
99 days
B.
101 days
C.
91 days
D.
115 days
E.
100 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!