Question: What is the _ LATEST EXPECTED COMPLETION TIME _ ? Question 1 Answer a . Is a worse case estimate of the project completion time
What is the LATEST EXPECTED COMPLETION TIME
Question Answer
a
Is a worse case estimate of the project completion time
b
The latest expected completion time is the latest time that a node can be reached, without delaying the whole project
c
It is the latest expected time that workers will be allowed home after a hard day of work
d
The latest expected completion time is the time needed to complete the whole project
e
It is the deadline set by the customer that must be met
Clear my choice
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock