Question: What is the LS for Node C? (a) 9 (b) 10 (c) 17 (d) 18 What is the LF for Node E? (a) 17 (b)

What is the LS for Node C? (a) 9 (b) 10 (c) 17

What is the LS for Node C?

(a) 9

(b) 10

(c) 17

(d) 18

What is the LF for Node E?

(a) 17

(b) 22

(c) 23

(d) 24

What is the ES for Node E?

(a) 10

(b) 16

(c) 17

(d) 22

What is the LF for Node D?

(a) 15

(b) 16

(c) 20

(d) 21

What is the slack in node D?

(a) 0 days

(b) 1 days

(c) 2 days

(d) 3 days

What is the critical path?

(a) A~B~D~F~G

(b) A~C~E~G

(c) A~B~E~F~G

(d) A~B~E~G

AON Draw the project network schedule / activity on node diagram, label each node with ES/EF & LS/LF schedules according to the method from class starting with day 0. Then answer through question 7 with your diagram. We have a project (Cardinal), with these activities in days: Activity B D Immediate Predecessor None A A B BC D E, F Estimated Duration (Days) 3 13 7 4 8 3 12 E F G How long is this project scheduled to take? (a) 35 days (b) 36 days O (c) 37 days O (d) 38 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!