Question: What is the LS for Node C? (a) 9 (b) 10 (c) 17 (d) 18 What is the LF for Node E? (a) 17 (b)

What is the LS for Node C?
| (a) 9 | ||
| (b) 10 | ||
| (c) 17 | ||
| (d) 18 |
What is the LF for Node E?
| (a) 17 | ||
| (b) 22 | ||
| (c) 23 | ||
| (d) 24 |
What is the ES for Node E?
| (a) 10 | ||
| (b) 16 | ||
| (c) 17 | ||
| (d) 22 |
What is the LF for Node D?
| (a) 15 | ||
| (b) 16 | ||
| (c) 20 | ||
| (d) 21 |
What is the slack in node D?
| (a) 0 days | ||
| (b) 1 days | ||
| (c) 2 days | ||
| (d) 3 days |
What is the critical path?
| (a) A~B~D~F~G | ||
| (b) A~C~E~G | ||
| (c) A~B~E~F~G | ||
| (d) A~B~E~G |
AON Draw the project network schedule / activity on node diagram, label each node with ES/EF & LS/LF schedules according to the method from class starting with day 0. Then answer through question 7 with your diagram. We have a project (Cardinal), with these activities in days: Activity B D Immediate Predecessor None A A B BC D E, F Estimated Duration (Days) 3 13 7 4 8 3 12 E F G How long is this project scheduled to take? (a) 35 days (b) 36 days O (c) 37 days O (d) 38 days