Question: What is the most NEGATIVE impact for a firm using the priority rule of shortest processing time (SPT) to schedule production through its factory? Some

What is the most NEGATIVE impact for a firm using

What is the most NEGATIVE impact for a firm using the priority rule of shortest processing time (SPT) to schedule production through its factory? Some orders with longer processing times may be delivered late to customers Some orders are completed earlier than customer require them Some orders will be split to take advantage of capacity slack time Some orders will be batched with similar processing times