Question: What is the Multifactor productivity for the Blue Space Inc if they have the following data? Units produced: 5,000 Standard price: $30/unit Labor input: 500
What is the Multifactor productivity for the Blue Space Inc if they have the following data?
Units produced: 5,000
Standard price: $30/unit
Labor input: 500 hours
Cost of labor: $25/hour
Cost of materials: $5,000
Cost of overhead: 2x labor cost
- What is the multifactor productivity for the produced units?
Step by Step Solution
3.51 Rating (154 Votes )
There are 3 Steps involved in it
To calculate the multifactor productivity we first need to calculate the total input ... View full answer