Question: What is the network slack time assuming the customer satisfaction calls for the project to be completed in 21days? Cal. The slack time for all

What is the network slack time assuming the customer satisfaction calls for the project to be completed in 21days? Cal. The slack time for all events not on the critical path
Activity Initial Node Final Node UDS PESTISTIC MOST LIKELY Time Estimate Time Estimate Time Estimate 1 2 3 2 B 11 4 6 5 36 1 3 6 5 D 2 6 4 3 E 2 4 3 2 F 3 4 2 4 3 G 3 5 15 9 H 4 6 CH 6 5 4 14 10 4 5 1 3 2 5 7 K 2 4 3 6 14 10Step by Step Solution