Question: What is the probability that the project will take longer than 44 weeks? Brett wants to ensure that the probability of completing the project in
What is the probability that the project will take longer than 44 weeks?
Brett wants to ensure that the probability of completing the project in 32 weeks is at least 80%. By how many weeks should the expected project duration be shortened? Crashing activities do no affect outcome
A critical path is 43 weeks, the deviation is 3.59.
50-43/3.59= 1.94 Z=1.94 Probability z=1.94 = .9738 0r 97.38% 50 weeks
Can use the same formula for above?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts