Question: Consider a project that is expected to be completed in 30 weeks with following normal distribution plot. The shaded area in the plot is 30%

Consider a project that is expected to be completed in 30 weeks with following normal distribution plot. The shaded area in the plot is 30% of the total area under the curve, 30 32 What is the probability that the project will take longer than 32 weeks? the 0.72 2-score represents a probability of 76,42%) 76.42 22.58% 70
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock