Question: What is the project duration? Using any approach you wish ( eg . trial and error ) develop a loading chart for resources, Electrical Engineer
What is the project duration? Using any approach you wisheg trial and error develop a loading chart for resources, Electrical EngineerEE and resource, Mechanical Engineer ME Assume only one of each resource exists. Given your resource schedule compute early, late and slack times for the project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects? Fill in the times below for a resource activity schequle.