What is the purpose of the performance measurement baseline (PMB) Assessment activity in the Integrated Baseline Review
Fantastic news! We've Found the answer you've been seeking!
Question:
What is the purpose of the performance measurement baseline (PMB) Assessment
activity in the Integrated Baseline Review (IBR) process?
A: For contracts with an earned value management (EVM) requirement, the DoD policy on IBRs is assessed to determine if it applies.
B: To conduct control account manager discussions in order to assess the PMB
C: To assemble an IBR tram to assess the PMB during the OBR event
D: As part of the ongoing management of a contract the PMB is assessed to determine when an IBR event is needed.