Question: What is the slack for activity B ? A . 0 B . 1 C . 2 D . 3 What is the expected duration

What is the slack for activity B? A.0 B.1 C.2 D.3 What is the expected duration of this project? A.17 B.18 C.19 D.20 Below are the project steps for the creation ofa television advertisement for Foolio, which is a new energy drink that the musician Coolio has created. Consider the following data for questions 1 through 5: Duration Description Activityls) Preceding Activity(days Create script for advertisement Book technical crew Book actors A Create propsBC and costumes Book location C Filming and editing 342 D, E