Question: PLEASE ANSWER 14, 15, AND 16 Based on the network diagram of a project shown above, answer Questions 8 through 17. All the numbers in


Based on the network diagram of a project shown above, answer Questions 8 through 17. All the numbers in the diagram are in weeks. What is the latest time activity " C " can finish, i.e., what is the LF of activity " C "? 11 13 8 6 Question 15 (1 point) What is the slack of activity "C"? 4 0 2 1 Which of the following activities is not critical for the project? A B E D