Question: What is the slack time for Activity C given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 4 --
What is the slack time for Activity C given the activity times and precedence requirements shown in the table?
| Activity | Time | Predecessor |
| A | 4 | -- |
| B | 7 | -- |
| C | 8 | A |
| D | 2 | A |
| E | 4 | B |
| F | 5 | C, D |
| G | 9 | E, F |
| H | 7 | G |
a.
None of the above
b.
3
c.
1
d.
0
e.
2