Question: What is the slack time for activity D? What is the earliest start time for activity F? What is the latest finish time for activity


What is the slack time for activity D?
What is the earliest start time for activity F?
What is the latest finish time for activity H?
Which of the following is the critical path at the beginning of the analysis?
-ABCFJ
-ABDGJ
-ABCEIJ
-ABCEHJ
What is the first activity that Egon should crash?
Activity C can be crashed how many times?
What is the minimum completion time for the project after crashing?
If Egon has a budget of only $2,000 for crashing costs, what is the shortest possible completion time?
How much will it cost Egon to reduce the original total project time by three weeks?
How much did crashing that last (third) week cost Egon?
Please answer all and show work! Studying for an exam!!
Use the following information for questions 17 to 26. Egon Spengler is planning a charity benent gala for his "Save the city campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get everything done before the weekend of the gala. Egon has created a list of tasks, their time requirements, and their relationships. He has also begun a network diagram, but needs to know what to do next. He knows that he needs to reduce the total time by three weeks Ach Duration Crash Activity weeks) Time Description " (weeks) Preceding Crashing Activitylles) Cost/Week Determine gala theme $900 B 5 5 Reserve portal location for gala $1.020 Create Marketing Plan $980 D 6 6 Ray Parker, Jr.to audition musical B $1,500 acts Determine ticket sales method $630 Purchase supplies. including Stay F 7 5 5700 Putt marshmallows Pick musical actD and sign contract $550 Sell tickets in person $690 I 5 5 Sell tickets online E $1,150 Gala! H, I,F,G QO DOO What is the slack time for activity D?Enter your answer as a numerical whole number. Question 18 What is the earliest start time for activity F? (i.e. What is the earliest week activity F can start?) Enter your answer as a numerical whole number. Question 19 What is the latest finish time for activity H? 25 26 29 .30 Question 20 Which of the following is the critical path at the beginning of the analysis? ABCFJ ABDGJ ABCEI o Question 21 What is the first activity that Egon should crash? Question 22 Activity C can be crashed how many times? -0 Question 23 What is the minimum completion time for the project after crashing (until no more crashing is possible)? 27 weeks 28 weeks 29 weeks 30 weeks Question 23 What is the minimum completion time for the project after crashing (until no more crashing is possible)? 27 weeks 28 weeks 29 weeks 30 weeks Question 24 If Egon has a budget of only $2,000 for crashing costs, what is the shortest possible completion time? 27 weeks 28 weeks 29 weeks 30 weeks Question 25 How much will it cost Egon to reduce the original total project time by three weeks? $1.530 $2,510 $3,550 $4,150 Question 26 How much did crashing that last (third) week cost Egon? $630 $900 $980 $1000 Question 27 Slack in a project activity can be found by taking either the difference between the late start and early start of an activity or the late finish minus the early finish of an activity. True False