Question: * ) What is the takt time for each line? What is the theoretical minimum number of workstations needed on each line? ( * *

*) What is the takt time for each line? What is the theoretical minimum number of workstations needed on each line?
(**) Make workstation assignments using the largest eligible task rule. Calculate the cycle time, idle time, percent idle time, and efficiency delay for the resulting line.
(***) Given the task times listed above, what is the minimum cycle time that can be achieved by a line? What is the maximum daily output that could be achieved by a single line?