Question: What is the total project overhead for a project that lasts 3 months and has the following costs? Labor is $4,000; materials are $9,500; equipment
What is the total project overhead for a project that lasts 3 months and has the following costs? Labor is $4,000; materials are $9,500; equipment rentals are $1,200; superintendent's annual salary is