Question: What is the variance for the critical path? table [ [ Activity , table [ [ Optimistic ] , [ Time ] ,

What is the variance for the critical path?
\table[[Activity,\table[[Optimistic],[Time],[(Weeks)]],\table[[Most],[Likely],[Time (],[weeks)]],\table[[Pessimistic],[Time],[(weeks)]]],[A,8,10,12],[B,4,10,16],[C,4,5,6],[D,6,8,10],[E,4,7,12],[F,6,7,9],[G,4,8,12],[H,3,3,3]]
9.91
6.66
5.13
5.6
 What is the variance for the critical path? \table[[Activity,\table[[Optimistic],[Time],[(Weeks)]],\table[[Most],[Likely],[Time (],[weeks)]],\table[[Pessimistic],[Time],[(weeks)]]],[A,8,10,12],[B,4,10,16],[C,4,5,6],[D,6,8,10],[E,4,7,12],[F,6,7,9],[G,4,8,12],[H,3,3,3]] 9.91